Elevated view of leafy Thousand Oaks homes with a small cluster of low-rise residences beyond, framed by golden hills and a clear blue sky.

Where Thousand Oaks Will Change Between Now And 2032

November 19, 2026

"Although there are only 340 units permitted in 2025, there are approximately 1,600 residential units with approved entitlements, including 263 deed-restricted affordable units, that are in the pipeline," Ian Holt, a senior planner for the City of Thousand Oaks, told the Thousand Oaks Acorn in March 2026. In the same report, he said permits are backlogged because of interest rates, insurance costs and construction expenses.

The largest projects named in local reporting are apartment complexes on Thousand Oaks Boulevard, on Hampshire Road and in the Hillcrest Drive and Rancho Conejo area of Newbury Park. The biggest single project is the city's own downtown at the Civic Arts Plaza, which the City Council approved on July 7, 2026, with a construction schedule running to 2032. For a buyer comparing parts of Thousand Oaks, this means the change ahead is concentrated in a few places, and the established single-family neighborhoods are not where it is happening. The real choice is how close you want to live to it.

The Downtown Approved On July 7

The Downtown Thousand Oaks Project covers about 17.6 acres at 2100 E. Thousand Oaks Boulevard. According to the city's environmental record for the project, the site is bounded by Thousand Oaks Boulevard to the north, Highway 101 to the south, Conejo School Road to the east and the end of Oakwood Drive to the west.

The approved plan has four new buildings:

  • a seven-story, 142-key hotel
  • a seven-story mixed-use building with 161 apartments, 26 of them affordable
  • a four-story mixed-use building with 79 apartments, 13 of them affordable
  • a two-story restaurant building

It also includes a public park with a splash pad, a children's play structure, informal stages and open lawn, plus an outdoor amphitheater and a partial rebuild of City Hall. The plan removes 53 protected trees and plants 159 replacements on and off the site.

The plan's Specific Plan area also takes in 2150 and 2200 E. Thousand Oaks Boulevard, the Lakes property next door, though that land is not part of the construction area.

The city has done the design and entitlement work itself. It plans to choose a private partner to build and run the hotel and mixed-use buildings through a competitive process, and its project FAQ expects that selection in the first quarter of 2027. Qualifications from interested developers were due November 18, 2026.

The Calendar Runs To 2032

The city's procurement documents lay out the phases in order.

  1. Phase 1: site work. This includes realigning a Ventura County Watershed Protection District concrete box culvert, building West Street, extending Oakwood Drive, new utilities and partial demolition of non-structural parts of the Civic Arts Plaza.
  2. Phase 2A: the private mixed-use buildings and hotel on the Westside Parcel.
  3. Phase 2B: the park and restaurant pad. The city's background section also describes this phase as a Carpenter Park renovation.
  4. Phase 2C: reuse of City Hall, including a public market.
  5. Phase 3: the amphitheater.

The city's preliminary timeline has Phase 1 design running from September 2026 through mid-2028 and Phase 1 construction starting in late 2028. The environmental record describes five phases beginning in 2027 and finishing by 2032. A separate city project, the Oakwood Improvement Project, adds curb, gutter, sidewalk, drainage and road widening along Oakwood Drive.

So a household that buys near the Civic Arts Plaza this winter could live with design work, then culvert and road construction, then building construction, for most of the next six years. The park, public market and amphitheater come near the end of that schedule.

The Rest Of The Pipeline Follows The Same Pattern

Away from downtown, the largest approved projects are also apartments, and they are spread along the Boulevard, Hampshire Road and Newbury Park. In November 2025, the Thousand Oaks Acorn described a wave of long-approved projects finally reaching construction.

Project Location Homes Status in local reporting
T.O. Ranch, IMT Residential Former Kmart site, Hampshire Road 420, including 50 low-income Crews active in October 2025 after a state-required soil cleanup
Oakwell, The Latigo Group 2150 W. Hillcrest Drive, near Rancho Conejo 333, plus 6,500 sq. ft. of retail Approved in 2023; Latigo lists expected completion in 2026
The Sanctuary Former Timber School site, Newbury Road 218 in nine buildings Under construction in October 2025
500 Thousand Oaks Boulevard Six-acre site of the pumpkin patch and Christmas tree lot 328, including 44 lower-income Approved; not yet under construction as of November 2025
384 Erbes Road Former Hillcrest School site 78 three-story townhomes for sale Approved as a city-funded affordable project

A few details matter to anyone who knows these sites. At the Timber School, where the Conejo Valley's first public school stood, the 1924 schoolhouse and the 1948 auditorium are being kept and converted into a leasing office, co-working space, clubhouse and children's lounge. The Kmart on Hampshire Road opened in 1982 and closed in 2004, and the lot sat vacant for nearly two decades. Oakwell's site briefly held Thousand Oaks City Hall starting in 1989 and later became part of the Amgen campus.

The project's path has had changes along the way. In April 2026, the Ventura County Star reported that the City Council turned down the developer's cost-cutting changes to Oakwell and was reviewing new plans.

The only for-sale homes on that list are the Erbes Road townhomes, and they are reserved for households at set income levels. The Acorn's roundup of current and upcoming projects lists no new single-family subdivision.

What This Means For A Buyer Comparing Neighborhoods

Around 1,600 entitled units, the downtown's 240 apartments and the T.O. Ranch, Oakwell and Sanctuary complexes add up to a large increase in Thousand Oaks rentals. Little of it adds to the supply of detached houses on lots. Owner households thinking about the next few years will mostly feel this through new places to eat, gather and shop, and through traffic and construction near the Boulevard and Hillcrest. They will not feel it as new houses competing with theirs for buyers.

Countywide figures give some context. The California Association of Realtors' September 2026 report, released October 19, put Ventura County's median price for existing detached homes at $930,000 for September 2026, up 3.3% from September 2025. Detached-home sales were up 6.4% over the same period. County inventory was 3.5 months of supply in September 2026, down from 3.8 months a year earlier, and median time on market was 38.5 days, compared with 37 days in September 2025. These are county figures for detached homes only, not Thousand Oaks numbers. They describe a market where more homes are selling and inventory is a little tighter than last year, with apartment construction happening alongside it.

In practice, the decision looks different depending on where you are shopping:

  • Close to the Civic Arts Plaza and Thousand Oaks Boulevard: you are buying near a downtown that does not exist yet. The park, the public market in the reused City Hall and the amphitheater come in the later phases, after site work that the city expects to start in late 2028.
  • Near Hillcrest and Rancho Conejo in Newbury Park: Oakwell and the Timber School apartments are close by, and the change there arrives sooner because those buildings are already further along.
  • Established hillside and estate neighborhoods: the approved pipeline barely reaches these areas. For buyers who want the lot, the view and a quiet street, the main questions are about the specific house and its price, not new construction coming next door.

Neither choice is wrong. A buyer who wants to walk to dinner and a show in 2032 may pick a different street from a buyer who wants the next six years to look like the last six. Our Thousand Oaks neighborhood page and the buyer resources are good starting points for comparing them. Sellers near either corridor can see how recent sales are pricing through our home valuation tool.

A Short FAQ

Where exactly is the new downtown? It is at the Civic Arts Plaza, 2100 E. Thousand Oaks Boulevard, between the Boulevard and Highway 101 and from Conejo School Road west to the end of Oakwood Drive.

When does construction start? The city's preliminary schedule has Phase 1 site and utility construction beginning in late 2028, after design that runs through mid-2028.

Who is building the hotel and apartments? The city expects to choose a partner developer in the first quarter of 2027. RRM Design Group is the design consultant for the overall project, with Smith Group and KPFF as lead subconsultants.

What happens to the pumpkin patch lot on Thousand Oaks Boulevard? The six-acre site at 500 Thousand Oaks Boulevard is approved for 328 homes in three buildings, with about 8,500 square feet of retail and restaurant space.

If you are weighing Thousand Oaks addresses near the Boulevard against ones farther away, Jaime Krupnick would be glad to go over the downtown schedule and the homes you are considering with you. Request a Private Consultation.

Work with Jaime

Work with Jaime

From first conversation to closing day and beyond, Jaime delivers a true concierge experience. She guides clients through every step of buying and selling with clarity and confidence, backed by a trusted team of top-tier professionals. Her team can assist every step from staging and design to photography, inspections, contractors and lending, ensuring the process feels seamless, elevated and exceptionally well managed.